Category: Monthly Webinar Latest ABC Innovations in Railway Bridges in the U.S.

September 15, 2016 1:00 pm

by Kevin Eisenbeis, P.E., Director of Bridges, Burns and McDonnell

Webinar Documents

Description: Accelerated bridge construction has been the standard for railway bridges for many years in the US and abroad. The need to keep freight and people moving continues to make minimized down time the priority for railway bridge replacements. So, what is new in ABC for railway bridges? This presentation describes the latest ABC innovations in railway bridges in the US and includes design and construction details for a recent typical railway bridge replacement that had a minimal total down time. Lessons learned and future trends will also be discussed.

September 2016_Photo 1_Precast elements with brief track outage

Precast elements with brief track outage

September 2016_Photo 2_Replacing timber trestle bridge under live rail traffic

Replacing timber trestle bridge under live rail traffic

September 2016_Photo 3_Lateral slide – through plate girder bridge

Lateral slide – through plate girder bridge

September 2016_Photo 4_Truss span float-in

Truss span float-in