November 4, 2014 N/A
The 2014 in-depth web training features the Massachusetts DOT's 93FAST14 project. In this project ABC was used in the replacement of 14 bridges on Interstate 93 in Medford, Middlesex Country. The bridge superstructures were installed during 55-hour weekend closures over a 10 weekend period during the summer of 2011.
Module 1: Introduction
by Tom Donald, P.E., Director of Bridge Project Management, MassDOT
- MassDOT’s Accelerated Bridge Program
- Overview of 14 bridge replacements in 10 weeks
- Decision to use Design Build
- Post-construction inspection and performance
Module 2: Planning and Preliminary Design
by Mike Culmo, P.E., Vice President, Transportation and Structures, CME Associates, Inc.
- History of project development
- Project priorities
- Decision for use of ABC vs conventional construction
- Cost implications of ABC vs. Conventional
- Overall project timeline / schedule
- Prefabrication options and preliminary design approach
- Preliminary Substructure Analysis
- Performance specification for closure pours
- Roles and responsibilities
Module 3 :Design Details – Substructure Rehabilitation
by Joe Gill, P.E., President, Gill Engineering
- Design requirements
- Substructure analysis
- Issues with applying LRFD to existing substructure
- Rational approach used
- Bearing seat modifications
- Requirements for shallower beams
- Different beam spacing
- Shoring and beam end removal for beam seat modifications
- Abutment modifications
- Use of approach slabs as dead-men
Module 4: Design Details – Superstructure Replacement
by Joe Gill, P.E., President, Gill Engineering
- Design requirements
- No real design differences
- Designed as simple spans with link slabs
- Minimize beam depth to improve vertical clearance
- Complications associates with large skews
- Diaphragms
- Minimize the number of diaphragms
- Use of diaphragms on closure pour bays
- Cast-in-place barriers
- Why not precast?
- Use of shoulders for work zone.
- Construction issues
- Crane picks controlled most sites
- Minimize weight on PBUs
- Closure pour issues
- High early strength
- Control of shrinkage to minimize cracking
- Details and reinforcing
- Design for interim strength
- Link slab design – jointless deck
- Slab details at abutments
- Diaphragms
- Bearing layout and design
- Floating Bridge Concept
- Use of sliding bearings to control seismic forces
- Deck protection – HMA and waterproofing vs. exposed deck
Module 5: Preliminary Construction Planning
by Kevin Lampron, Jr. P.E., Area Manager, J.F. White Contracting Company
- Minimum required information
- Contractor experience requirements
- Innovative contracting strategies
- Timeline and schedule
- Plans
- Specifications
- Incident management strategies
Module 6: Construction
by Kevin Lampron, Jr. P.E., Area Manager, J.F. White Contracting Company
- Contractor options
- Site access / location constraints
- Construction timeline / schedule
- Quality Control / Construction inspection